Public procurement (last 12 months)
Contracts first signed in the last 12 months.
The 12-month window is by original contract signing date: it covers contracts first signed in the period, and excludes amendments registered in the period to contracts signed earlier. Amounts are in KRW from Korea's Public Procurement Service (KONEPS). The 12-month total counts sole contracts in full and joint contracts by the supplier's share; joint contracts without a published share are counted but not summed. Multi-year contracts count only the current-period amount. Unit-price (framework) contracts are reported separately because their values are ceilings, not spend.
| Aggregation Period | 2025-11-01 to 2026-10-31 (basis: original_signed_date) |
| 12-Month Procurement Amount | KRW 2,775,520,410 |
| 12-Month Contract Count | 7 (Joint contracts: 0) |
| Unit-Price (Framework) Contracts (Reported Separately) | 1 contracts | Ceiling: KRW 1,445,400,000 |
| Procurement Source | https://www.g2b.go.kr (verified: 2026-11-02T04:36:11.608Z) |
By Procurement Category
| Category | Contracts | 12M Counted Amount (KRW) |
| Goods (물품) | 7 | KRW 2,775,520,410 |
| Construction (공사) | 0 | KRW 0 |
| Services (용역) | 0 | KRW 0 |
| Foreign Procurement (외자) | 0 | KRW 0 |
By Contract Type
| Contract Type | Contracts | Supplier Share / Current Amount (KRW) | Total Contract Ceiling / Multi-year Total (KRW) |
| Lump-sum / Standard (총액·일반) | 6 | KRW 2,775,520,410 | KRW 0 |
| Multi-year / Continuing (장기·계속비) | 0 | KRW 0 | KRW 0 |
| Unit-price / Framework Ceiling (단가·제3자단가 — excluded from 12M total) | 1 | KRW 1,445,400,000 | KRW 0 |
| Unclassified / Zero-amount (기타) | 0 | KRW 0 | KRW 0 |
Top 5 Government Buyers
| Buyer (Korean Legal Name) | Agency Code | Contracts | 12M Amount (KRW) |
| 한국지역난방공사 | B550373 | 2 | KRW 1,313,042,460 |
| 새만금개발청 | 1730000 | 1 | KRW 806,560,760 |
| 대통령경호처 | 1021100 | 1 | KRW 373,786,000 |
| 코레일테크주식회사 | Z013121 | 1 | KRW 271,193,190 |
| 전남광주통합특별시 도시철도건설본부 | 6130674 | 1 | KRW 10,938,000 |
Recent Contracts (up to 7)
| Signed Date | Contract No. (KONEPS) | Contract Title (KO) | Category / Type | Buyer (KO) | Contract Amount (KRW) | Participation |
2026-06-11 (chg: 2026-07-20) |
R26TA01949897 |
김해전기사업소 옥외 고압배전반 구매 |
goods / lump_sum |
코레일테크주식회사 |
KRW 271,193,190 |
Sole (100%) |
2026-05-12 |
R26TA01845467 |
광주도시철도 2호선 차량기지 MOF 교체 설치 |
goods / lump_sum |
전남광주통합특별시 도시철도건설본부 |
KRW 10,938,000 |
Sole (100%) |
2026-05-07 |
R26TA01823548 |
영등포 2정수장 송수펌프동 전력설비 교체 고압배전반 제작설치 |
goods / unit_price |
서울특별시 서울아리수본부 |
KRW 1,445,400,000 |
Sole (100%) |
2026-04-16 |
R26TA01750173 |
경호안전교육원 3단계사업 전기공사 관급자재 구입(수배전반) |
goods / lump_sum |
대통령경호처 |
KRW 373,786,000 |
Sole (100%) |
2026-03-25 |
R26TA01660008 |
용인지사 용인열원 특고압배전반 구매설치 |
goods / lump_sum |
한국지역난방공사 |
KRW 766,000,000 |
Sole (100%) |
2026-01-12 (chg: 2026-06-17) |
R26TA01329087 |
데이터센터 배전반 구매 설치 |
goods / lump_sum |
한국지역난방공사 |
KRW 547,042,460 |
Sole (100%) |
2025-12-29 |
R25TA01267008 |
새만금산단 방류관로 건설사업 관급자재 구매(수배전반) |
goods / lump_sum |
새만금개발청 |
KRW 806,560,760 |
Sole (100%) |